Zenith 601 XL-B Build Log

Detailed construction log of Zenair Zodiac 601 XL Serial #6964

  • The Beginning
  • Wing
  • Empennage
    • Horizontal Stabiliser
    • Elevator
    • Rudder
  • Fuselage
  • Engine
  • Tools
  • Materials
  • Upgrade

Nose Ribs

Posted on April 27, 2008August 3, 2008 by Glenn

Continue forming nose ribs. Also spent some time adding stiffening gusset to brake.

5.07 hours.

Posted in Wing

Post navigation

Previous: Nose Ribs
Next: Nose ribs

Related Posts

  • Wing

Spars, fuel tank skins.

  • Glenn
  • April 25, 2009
  • 0

Re-check Spar Web markings, de-burr edges prior to drilling. Cut Fuel Tank Skins to size. 4.33 Hours.

  • Wing

Flanging Wing Ribs

  • Glenn
  • April 10, 2009
  • 0

Trialled flanging ribs by lowering car from jack onto rib positioned in dies. Works okay. 2.00 Hours.

  • Wing

Nose Ribs

  • Glenn
  • April 25, 2008
  • 0

De-burr nose rib blanks, formed first two nose ribs. 2.90 hours.