Posted on July 5, 2009March 7, 2010 by Glenn

6-B-8 9 Lower Bearing Support.

1.8 hours.

Posted in Fuselage

Post navigation

Previous: Tie Down Rings, Torque Tube Bearing
Next: Elevator

Related Posts

  • Fuselage

Fuselage Parts

  • Glenn
  • October 25, 2008
  • 0

Perform inventory of parts made, pull out next 0.025 sheet,

  • Fuselage

Baggage Bulkhead Form Block

  • Glenn
  • February 16, 2009
  • 0

Mark out Baggage Back Bulkhead form block. 0.95 Hours.

  • Fuselage

Fuselage Form Blocks

  • Glenn
  • February 17, 2009
  • 0

Instrument Panel & Middle Bulkhead form blocks marked out. 1.58 Hours.