Skip to content
Tuesday, October 6, 2026

Zenith 601 XL-B Build Log

Detailed construction log of Zenair Zodiac 601 XL Serial #6964

  • The Beginning
  • Wing
  • Empennage
    • Horizontal Stabiliser
    • Elevator
    • Rudder
  • Fuselage
  • Engine
  • Tools
  • Materials
  • Upgrade

Rudder Skeleton

Posted on March 23, 2008July 22, 2008 by Glenn

Continue with rudder build- drill and cleco doublers to spar.

3.83 hours.

Posted in Empennage

Post navigation

Previous: 6-T-4 5 Rudder Spar Doublers
Next: Rudder Skeleton

Related Posts

  • Empennage

6-T-4 5 Rudder Spar Doublers

  • Glenn
  • March 22, 2008
  • 0

Modify brake, then on advice from Debo Cox and Dave Clay left extra 100mm on material before bending, then decided to add extra bolts in […]

  • Empennage

Rudder Tip Rib

  • Glenn
  • January 28, 2008
  • 0

After three more attempts and experiments I finally arrived at one I was happy with. One of the problems I had was the plans are […]

  • Empennage

Rudder Skin

  • Glenn
  • May 18, 2008
  • 0

Rudder skin- made second rudder skin, good bend in improved brake, complete bend by gradually cramping down to rounded 1/4″ plywood strip- excellent results this […]

Copyright © 2026 Zenith 601 XL-B Build Log Theme: Zenith By Glenn Andressen.