Rudder Skeleton

Posted on December 27, 2008December 28, 2008 by Glenn

Re-assemble primed rudder skeleton, begin riveting.

0.75 Hours.

Posted in Empennage

Post navigation

Previous: Wingtip Top Angles
Next: Rudder Skeleton

Related Posts

  • Empennage
  • Horizontal Stabiliser

Stabiliser Form Blocks

  • Glenn
  • August 5, 2007
  • 0

I started making the form blocks for the stabiliser along with all of the wing form blocks. I used 18mm MDF, rough cutting them with […]

  • Empennage

Elevator

  • Glenn
  • July 26, 2009
  • 0

Elevator construction. 5.92 hours.

  • Empennage

Rudder Skeleton

  • Glenn
  • March 24, 2008
  • 0

Re-make nose rib again- not 100% happy with last one. Continue with rudder build- drill and cleco ribs to spar. 7.33 hours.