Skip to content
Monday, February 23, 2026

Zenith 601 XL-B Build Log

Detailed construction log of Zenair Zodiac 601 XL Serial #6964

  • The Beginning
  • Wing
  • Empennage
    • Horizontal Stabiliser
    • Elevator
    • Rudder
  • Fuselage
  • Engine
  • Tools
  • Materials
  • Upgrade

Rudder Skeleton

Posted on March 23, 2008July 22, 2008 by Glenn

Continue with rudder build- drill and cleco doublers to spar.

3.83 hours.

Posted in Empennage

Post navigation

Previous: 6-T-4 5 Rudder Spar Doublers
Next: Rudder Skeleton

Related Posts

  • Empennage

Rudder Nose Skin

  • Glenn
  • August 24, 2008
  • 0

Align, drill and cleco rudder nose skin.

  • Empennage

Elevator ribs

  • Glenn
  • December 15, 2007
  • 0

Completed elevator ribs.   2.17 hours.

  • Empennage
  • Horizontal Stabiliser

Stabiliser Ribs

  • Glenn
  • December 2, 2007
  • 0

I formed the stabiliser ribs as per the wing ribs, sandwiched between a form block and a blank. These all have a flange on the […]

Copyright © 2026 Zenith 601 XL-B Build Log Theme: Zenith By Glenn Andressen.