Posted on March 23, 2008July 22, 2008 by Glenn

Continue with rudder build- drill and cleco doublers to spar.

3.83 hours.

Posted in Empennage

Post navigation

Previous: 6-T-4 5 Rudder Spar Doublers
Next: Rudder Skeleton

Related Posts

  • Empennage
  • Horizontal Stabiliser

Stabiliser Assembly

  • Glenn
  • March 28, 2008
  • 0

Preparing the Stabiliser Skeleton Some of these components were 0.040 and 0.063 and I ordered them from Zenith, given the problems I’d had bending anything […]

  • Empennage

Rudder Nose Skin (Rebuilt)

  • Glenn
  • June 7, 2008
  • 0

ZAC responded to my enquiries and advised my skin fit was fine, however, I noticed during the week a smiley on one face. Only small, […]

  • Empennage
  • Horizontal Stabiliser

Stabiliser Ribs

  • Glenn
  • December 2, 2007
  • 0

I formed the stabiliser ribs as per the wing ribs, sandwiched between a form block and a blank. These all have a flange on the […]