Rudder Tip Rib

Posted on January 27, 2008July 22, 2008 by Glenn

Began forming rudder tip rib. Fully expected this would require several attempts!

3.57 hours

Posted in Empennage

Post navigation

Previous: Rudder nose rib
Next: Rudder Tip Rib

Related Posts

  • Empennage

Rudder Skeleton

  • Glenn
  • March 24, 2008
  • 0

Re-make nose rib again- not 100% happy with last one. Continue with rudder build- drill and cleco ribs to spar. 7.33 hours.

  • Empennage

Rudder nose rib

  • Glenn
  • January 26, 2008
  • 0

Began forming the rudder nose rib. Realised I would probably not get it right first time, but the first effort wasn’t too bad. 2.67 hours

  • Empennage

Elevator ribs

  • Glenn
  • December 15, 2007
  • 0

Completed elevator ribs.   2.17 hours.