Posted on January 27, 2008July 22, 2008 by Glenn

Began forming rudder tip rib. Fully expected this would require several attempts!

3.57 hours

Posted in Empennage

Post navigation

Previous: Rudder nose rib
Next: Rudder Tip Rib

Related Posts

  • Empennage

Rudder nose rib

  • Glenn
  • January 27, 2008
  • 0

Continued and made two more rudder nose ribs until I finished with one I was happy with. 2.58 hours.

  • Empennage

6-T-4 5 Rudder Spar Doublers

  • Glenn
  • March 22, 2008
  • 0

Modify brake, then on advice from Debo Cox and Dave Clay left extra 100mm on material before bending, then decided to add extra bolts in […]

  • Empennage

Elevator ribs

  • Glenn
  • December 15, 2007
  • 0

Completed elevator ribs.   2.17 hours.