Wing Spars February 2010

Date Job Start Time Finish Time Total Time Decimal
6/02/2010 Spar Upgrade Root Doublers 6-ZU-1 2 11:45 13:00 1:15 1.25
14:15 15:43 1:28 1.47
16:15 17:15 1:00 1.00
7/02/2010 Mark off, fit, drill & temp fasten Upgrade Doublers. Mark off Rear Channels 13:10 13:24 0:14 0.23
in prep for upgrade parts. Mark Main Spar wing attach holes ready for pre- 14:00 17:50 3:50 3.83
drilling. Spars will then be ready for de-burring, priming and riveting 0:00 0.00
13/02/2010 Spent some time evaluating how best to set dihedral and checking whether to 11:30 13:10 1:40 1.67
do it before riveting. Decide factory spars don’t come like that, so went ahead 14:50 17:50 3:00 3.00
and pulled apart temporarily fastened spars, de-burred and began scouring 0:00 0.00
in prep for priming. 0:00 0.00
14/02/2010 Continue scouring spars 15:30 17:21 1:51 1.85
18/02/2010 Spar scouring 13:50 14:00 0:10 0.17
20/02/2010 Spar scouring 11:30 13:15 1:45 1.75
14:30 17:49 3:19 3.32
21/02/2010 Spray port spar parts 11:45 13:15 1:30 1.50
Continue fabricating upgrade parts 6-ZU-1 3 Rib Angles 15:30 17:06 1:36 1.60
Third tank end 0:00 0.00
27/02/2010 Re- assemble port spar ready for riveting 13:43 14:00 0:17 0.28
14:30 15:00 0:30 0.50
15:35 18:10 2:35 2.58
28/02/2010 Set spar in jigs. 12:15 13:05 0:50 0.83
Practice solid riveting 13:50 15:10 1:20 1.33
Set first Spar rivets 15:30 18:13 2:43 2.72